The Rail Modernization at Union Station project was a three-phase plan to rehabilitate and modernize critical railroad infrastructure. Phase 1 replaced worn rail along the five tracks serving the station, Phase 2 replaced platform tracks and modernized the signal system, and Phase 3 upgraded tracks, signals, and related components.
The improvements replaced aging mechanical signals with modern electronic units, renewed switches, installed new crossovers, and modernized track infrastructure near Union Station to improve service.
Burns designed replacements for CP Mission and CP Terminal, two of the most complex locations in the Metrolink system. The firm’s design used split box technology to segment each track lead, providing flexibility for future operations and system maintenance.
Burns also performed the signal cutover for both control points, coordinating the work during a complete shutdown of the tracks into Union Station. Together, the split box control point designs and successful cutover helped support safer, more reliable service and positioned the system for future operational needs.
Location
Los Angeles, CA
Client
Southern California Regional Rail Authority
Industry
Expertise